Description

River’s Edge Walking Trail Phase IV will wrap around the lake between Gleneagles Drive and Gleneagles Way, ending at the club house on Plantation Parkway. The trail is just shy of one mile.

March 2024: A solicitation package has been posted and a pre-bid conference and site visit with potential contractors will be held on April 4. The deadline to submit a bid for the project is April 25.

February 2024: Prime Engineering has provided complete construction documents for the project. Planning, Design and Construction is working with Central Services to solicit bids for the project.

Budget

$5 million

Commission District

District 2

Served by Commissioner

Commissioner Felicia Franklin