Description

The new Fire Station No. 2 will be a replacement facility for the existing Fire Station No. 2 in Rex.

March 2024: Civil Design documents are projected to be completed by April 8 and will be submitted to the county for review.

February 2024: Planning, Design and Construction is awaiting cost estimates for a sewer connection installation. Architectural firm POND & Company is revising designs prior to submittal to Community Development and the Clayton County Water Authority for review.

January 2024: An adjustment to the initial design is necessary to accommodate Clayton County Water Authority stormwater requirements. POND & Company architectural firm has provided Planning, Design and Construction with plans to construct an underground storm water detention pond. Cost estimates are to be received by Jan. 26.

Budget

$4 million

Commission District

District 1

Design Firm

To Be Determined

Served by Commissioner