Description
The Fleet Maintenance Expansion Project will revitalize the existing facility to include an upgrade to its electrical system, new HVAC, vehicle lifts, flooring, windows, and doors. In addition, a new oil pump system and air lines are planned as well as painting the interior and exterior of the building.
March 2024: Moisture tests are being conducted on the first floor and demolition of the upstairs flooring is planned for mid-March. Interior bay painting and exterior building painting is dependent on weather conditions but are on the schedule to begin.
February 2024: The interior painting of the first and second floors has been completed. Exterior painting will begin when outside temperatures increase. Plans to replace the flooring are moving forward
January 2024: Replacement of lighting throughout the building has been completed and interior painting is now in progress to include hallways, kitchen, conference room, restrooms, front office, and reception area. Plans to paint the building exterior are on hold until warmer weather arrives.
Budget
$750,000
Commission District
District 4
Design Firm
Jericho Group
Served by Commissioner
Commissioner DeMont Davis