Description

Construction of a 6-ft wide concrete sidewalk along the west side of the roadway of Tara Boulevard in areas without existing sidewalk. Installing new Americans with Disabilities Act (ADA) compliant ramps and upgrading existing ramps which are not ADA compliant. Construction of concrete curb and gutter at various locations, pavement markings, roadway signage, and storm drain improvements. Existing sidewalk, and curb and gutter in need of repair will also be replaced.

Stage

Land
Concept
Design
Bidding
Construction
Completed
Budget

$174,839.00

Commission District

District 04

Design Firm

Not Applicable

Served by Commissioner

Commissioner DeMont Davis

Construction Firm

C & C Lovejoy LLC

Completion Date